Walk the line before you price it
-
Measure the run in segments
Every change of direction ends one segment and begins another. A single total length hides the corners, and corners are where the cost is.
-
Count posts rather than feet
Line posts fall on your spacing; corner, end and gate posts are set deeper, usually in more concrete and sometimes in a heavier size. They are priced separately because they are built separately.
-
Locate every gate
A gate is an assembly — two posts, hardware, a latch, and a hinge post carrying a swinging load — so it is priced as a unit rather than as the feet of fence it replaces.
-
Book the utility locate before you promise a start
Locates are not optional and they take days. A quote assuming a start date earlier than the locate can clear is a quote with a delay already built into it.
Terrain decides how the fence is built
A slope is handled either by racking the panels so they follow the ground or by stepping them and leaving a triangular gap beneath each one. Those are different amounts of labour and they look completely different when finished, so the quote should say which it prices — a client who pictured the other one has a fair complaint about a fence that is otherwise correct.
What moves a fencing number up
- Rock, roots or heavy clay, which turns post holes from an auger job into a jackhammer job
- No gate wide enough to get a machine into the yard, which puts every hole on a hand auger
- Removing and disposing of an existing fence, which is its own line and often its own dumpster
- Frost depth, which sets how deep every post goes and therefore how much concrete the job consumes
- A survey pin nobody can find, and a neighbour with an opinion about where the line runs
Say what the price is held against
Valid for 30 days, and name what that period covers: cedar and steel post prices come off the yard's current list, and lumber moves. It is worth adding that the quote covers the line as walked — a run re-routed afterwards is re-measured rather than adjusted, because moving one corner changes the post count and the post count is the price.
Common questions
- Why are corner posts priced separately?
- They carry tension from two directions, so they are set deeper and in more concrete than a line post and often in a heavier size. A run with six corners genuinely costs more than a straight run of the same length.
- Should a gate be included in the linear-foot price?
- No. A gate is posts, hardware and a hinge post carrying a swinging load, and it is priced as an assembly. Burying it in the per-foot rate makes every foot of plain fence look expensive to anyone comparing quotes.
- What happens if the ground turns out to be rock?
- Post holes stop being an auger job and become a jackhammer job, which can multiply the labour on the holes affected. It belongs in the exclusions so that hitting rock is a priced change rather than a loss.